Standard Deductions and Extra Allowances in Masonry and Plastering Quantity Take-offs

Navigating Openings, Deductions, and Special Finishes to Master Finishing Quantities

Written byLearnEng Team Updated October 23, 2026 English
Technical ArticleReading Content
Standard Deductions and Extra Allowances in Masonry and Plastering Quantity Take-offs banner
Views
2
  • Enhance Knowledge
  • Knowledge Sharing
  • Resource Networking

Free to join — save articles and keep learning.

LearnEng Team
LearnEng Team

Who is this article actually for?

Perfect for

  • You work in Infrastructure & Construction
  • You're a Civil & Structural / Quality & Management Standards professional
  • You have 3+ years of hands-on experience in this field

Before you enrol

  • Advanced level — assumes working knowledge of Civil & Structural
New to Civil & Structural? Browse beginner courses →

Article details

When preparing Bills of Quantities (BoQ) for civil and building works, structural quantities are typically straightforward. However, finishing trades—specifically masonry and plastering—frequently become battlegrounds for disputes. The difference between a profitable project and a margin-bleeding variation claim often lies in how standard deductions for openings and extra allowances for complex details are handled.

Understanding standard measurement codes (such as IS 1200, NRM2, or local building standards) is essential for accurate quantity take-offs.

1. Masonry Quantity Take-offs: Rules for Openings and Embedments

Brickwork or blockwork quantities are generally measured in cubic meters ($m^3$) or square meters ($m^2$) depending on thickness. When walls contain doors, windows, lintels, and structural columns, rules govern what must be deducted and what is ignored.

Standard Deduction Rules for Masonry

  1. Openings: No deduction is made for masonry volumes if an individual opening has an area of 0.5 square meters or less. For larger openings (doors, windows, ventilation ducts), the full sectional area of the opening is deducted from the masonry volume.

  2. Beams and Lintels: The volume of embedded lintels, sills, and tie beams running through walls is deducted from the masonry volume.

  3. Pillars and Columns: Concrete columns or brick piers embedded within the wall thickness are deducted so that overlapping volumes are not paid for twice.

What is Not Deducted in Masonry?

  • Wall plates, bed plates, and string courses of 10 cm depth or less.

  • Ends of joists, beams, rafters, and purlins passing through walls.

  • Chases, recesses, and holes left for utilities (provided their individual areas do not exceed standard threshold limits).

2. Plastering Quantity Take-offs: Thresholds and Complexities

Plastering is measured in square meters ($m^2$) based on the net surface area finished. Unlike masonry, plastering rules involve specific area thresholds for openings and mandate extra measurements for reveals, jambs, and soffits.

Deduction Rules for Plastering Openings

According to standard codes of measurement (e.g., IS 1200 Part 12), deductions for door, window, and opening areas follow a precise two-step logic:

  • Openings under 0.5 square meters: No deduction is made for the opening, and no extra allowance is added for finishing the jambs/soffits (it is considered balanced).

  • Openings between 0.5 and 3.0 square meters: The opening area is deducted once, but no addition is made for jambs/soffits unless specified.

  • Openings greater than 3.0 square meters: The full area of the opening is deducted, and the actual perimeter surface area of the jambs, sills, and soffits (reveals) is added back to the total plastering area.

3. Extra Allowances and Special Finishes

Quantity surveyors must capture intricate architectural details that require specialized labor and formwork. These extra items are billed separately per linear meter (running meters) or square meter.

Common Extra Items in Plastering and Masonry

  • Grooves and V-Joints: Architectural drip courses, expansion joints, or aesthetic grooves on exterior plaster facades.

  • Quoins and Cornices: Decorative corner bands, ornamental cornices, and bandings measured by length.

  • Formwork/Shuttering for Reveals: Extra formwork required to cast concrete window reveals or complex sills before plastering.

  • Chicken Wire Mesh (Expanded Metal): Added at structural junctions (where brickwork meets concrete columns or beams) to prevent plaster cracking. This is measured and paid for by area or linear length.

4. Summary Matrix: Masonry vs. Plastering Deduction Rules

Feature / Condition

Brick / Block Masonry (m3 or m2)

Wall Plastering (m2)

Small Openings (<0.5 $m^2$)

No deduction made

No deduction made; no jamb addition

Medium Openings (0.5 to 3.0 $m^2$)

Full deduction made

Deducted once; no jamb addition

Large Openings (>3.0 $m^2$)

Full deduction made

Deducted, and jambs/soffits added back

Embedded Elements (Lintels/Beams)

Deducted from masonry volume

Not applicable (surface finish covers junctions)

Conclusion

Mastering masonry and plastering take-offs requires meticulous attention to architectural drawings and adherence to established measurement codes. By correctly applying deduction thresholds for openings and ensuring that extra allowances for jambs, reveals, and joint meshes are accounted for, quantity surveyors protect project budgets from revenue leakage and eliminate ambiguous contractor claims.

Go deeper with a full course

Courses on the tools and skills this article covers.

Opportunities that await you!

Career opportunities

Free to read

Join EveryEng to save articles and keep learning

Why people choose EveryEng

Industry-aligned articles, expert knowledge, hands-on learning, and career-relevant topics — all in a flexible and supportive environment.

Put no limit on your engineering passion.

We would love to hear from you.

Engineers collaborating around a laptop