When preparing Bills of Quantities (BoQ) for civil and building works, structural quantities are typically straightforward. However, finishing trades—specifically masonry and plastering—frequently become battlegrounds for disputes. The difference between a profitable project and a margin-bleeding variation claim often lies in how standard deductions for openings and extra allowances for complex details are handled.
Understanding standard measurement codes (such as IS 1200, NRM2, or local building standards) is essential for accurate quantity take-offs.
1. Masonry Quantity Take-offs: Rules for Openings and Embedments
Brickwork or blockwork quantities are generally measured in cubic meters ($m^3$) or square meters ($m^2$) depending on thickness. When walls contain doors, windows, lintels, and structural columns, rules govern what must be deducted and what is ignored.
Standard Deduction Rules for Masonry
Openings: No deduction is made for masonry volumes if an individual opening has an area of 0.5 square meters or less. For larger openings (doors, windows, ventilation ducts), the full sectional area of the opening is deducted from the masonry volume.
Beams and Lintels: The volume of embedded lintels, sills, and tie beams running through walls is deducted from the masonry volume.
Pillars and Columns: Concrete columns or brick piers embedded within the wall thickness are deducted so that overlapping volumes are not paid for twice.
What is Not Deducted in Masonry?
Wall plates, bed plates, and string courses of 10 cm depth or less.
Ends of joists, beams, rafters, and purlins passing through walls.
Chases, recesses, and holes left for utilities (provided their individual areas do not exceed standard threshold limits).
2. Plastering Quantity Take-offs: Thresholds and Complexities
Plastering is measured in square meters ($m^2$) based on the net surface area finished. Unlike masonry, plastering rules involve specific area thresholds for openings and mandate extra measurements for reveals, jambs, and soffits.
Deduction Rules for Plastering Openings
According to standard codes of measurement (e.g., IS 1200 Part 12), deductions for door, window, and opening areas follow a precise two-step logic:
Openings under 0.5 square meters: No deduction is made for the opening, and no extra allowance is added for finishing the jambs/soffits (it is considered balanced).
Openings between 0.5 and 3.0 square meters: The opening area is deducted once, but no addition is made for jambs/soffits unless specified.
Openings greater than 3.0 square meters: The full area of the opening is deducted, and the actual perimeter surface area of the jambs, sills, and soffits (reveals) is added back to the total plastering area.
3. Extra Allowances and Special Finishes
Quantity surveyors must capture intricate architectural details that require specialized labor and formwork. These extra items are billed separately per linear meter (running meters) or square meter.
Common Extra Items in Plastering and Masonry
Grooves and V-Joints: Architectural drip courses, expansion joints, or aesthetic grooves on exterior plaster facades.
Quoins and Cornices: Decorative corner bands, ornamental cornices, and bandings measured by length.
Formwork/Shuttering for Reveals: Extra formwork required to cast concrete window reveals or complex sills before plastering.
Chicken Wire Mesh (Expanded Metal): Added at structural junctions (where brickwork meets concrete columns or beams) to prevent plaster cracking. This is measured and paid for by area or linear length.
4. Summary Matrix: Masonry vs. Plastering Deduction Rules
Feature / Condition | Brick / Block Masonry (m3 or m2) | Wall Plastering (m2) |
Small Openings (<0.5 $m^2$) | No deduction made | No deduction made; no jamb addition |
Medium Openings (0.5 to 3.0 $m^2$) | Full deduction made | Deducted once; no jamb addition |
Large Openings (>3.0 $m^2$) | Full deduction made | Deducted, and jambs/soffits added back |
Embedded Elements (Lintels/Beams) | Deducted from masonry volume | Not applicable (surface finish covers junctions) |
Conclusion
Mastering masonry and plastering take-offs requires meticulous attention to architectural drawings and adherence to established measurement codes. By correctly applying deduction thresholds for openings and ensuring that extra allowances for jambs, reveals, and joint meshes are accounted for, quantity surveyors protect project budgets from revenue leakage and eliminate ambiguous contractor claims.