Shoring in construction is temporary structural support. It holds soil, existing buildings, partially built work, formwork, or damaged structures in a safe position until the permanent structure or ground condition can carry the load. Good shoring is not just “putting props in”; it is a load path, designed and installed in the right sequence, then inspected until it is safely removed.
What Shoring Means in Construction
Shoring is the use of temporary supports to prevent movement, collapse, or overstress during construction, demolition, excavation, repair, or alteration work. The support may resist vertical loads, lateral loads, or both.
A useful way to think about shoring is: what is unstable without temporary help? The answer could be an excavation face, a wall with an opening cut into it, a slab being cast, a building next to a basement excavation, or a structure damaged by fire, impact, settlement, or age.
Shoring is different from scaffolding. Scaffolding primarily provides access and working platforms. Shoring primarily carries structural load or restrains movement. Some site systems can look similar, and a scaffold may be designed for special loads, but the engineering purpose is different.
It is also different from underpinning. Underpinning strengthens or deepens an existing foundation as a more permanent intervention. Shoring may be used during underpinning, but it is normally temporary. For a broader overview, see what is shoring and why do buildings need it.
Where and Why Shoring Is Used
Shoring is used wherever construction changes the normal load path or removes support that was previously keeping something stable. Common situations include excavations, building alterations, new concrete works, demolition, and emergency stabilisation.
Excavations and basement construction
When soil is cut vertically or at a steep angle, it may not stand safely by itself. Shoring supports the excavation sides and protects workers, nearby roads, utilities, and adjacent structures. This is common for basements, trenches, lift pits, underground services, pile caps, and retaining walls.
The reason is simple: excavating removes the soil that was providing lateral confinement. The remaining soil wants to move into the excavation, especially if it is loose, wet, loaded at the top, or affected by vibration.
Alterations to existing buildings
Shoring is often required when removing walls, columns, beams, or slabs in existing buildings. For example, if a load-bearing wall is removed to create a large opening, temporary shores may carry the floor and roof loads until the new beam or frame is installed and connected.
This work is risky because the existing load path may not be obvious. Old buildings may have hidden deterioration, undocumented modifications, or materials that do not match drawings. Temporary works must therefore be planned from actual site conditions, not only assumptions.
Concrete construction and formwork support
Fresh concrete has weight but no useful strength until it hardens. Formwork and falsework support wet concrete, construction live loads, reinforcement, workers, equipment, and sometimes impact or vibration. Backpropping or reshoring may be needed below recently cast slabs so that loads are distributed through several levels instead of overloading one young slab.
Demolition and emergency works
During demolition, stability changes continuously. Removing one element can increase load or unbraced length in another. Shoring may stabilise walls, floors, facades, or partially demolished frames.
Emergency shoring is used after structural damage, vehicle impact, fire, flood, earthquake, blast, or ground movement. The aim is to quickly create a safe load path and exclusion zone so rescue, inspection, or repair can proceed.
Main Types of Shoring Systems
The main types of shoring systems can be grouped by what they support: excavations, vertical building loads, lateral building loads, and special temporary works. The correct system depends on soil, depth, loading, access, duration, and movement tolerance.
Timber shoring
Timber shoring uses timber posts, walers, sheeting, wedges, and braces. It is often used for small works, repair jobs, and short-duration support where loads are moderate and site carpenters can adapt the system to irregular geometry.
Its advantages are flexibility and availability. Its limits are variability in timber quality, lower capacity compared with engineered steel or aluminium systems, and higher dependence on workmanship.
Steel shoring and props
Steel props, frames, beams, needle beams, soldiers, and struts are common for building support and excavation works. Adjustable steel props are widely used for slabs and beams; heavier-duty proprietary frames or towers support larger loads.
Steel systems are strong, reusable, and predictable when used within their rated capacity. However, they still need correct bracing, bearing, plumbness, connection, and protection against accidental impact.
Hydraulic shoring
Hydraulic shoring uses hydraulic cylinders, usually with aluminium or steel rails or panels, to support trench walls. The system can often be installed from above the trench, reducing worker exposure during installation.
It is common in utility trenching where the work progresses along a linear route. Suitability depends on trench depth, soil type, water conditions, surcharge loads, and manufacturer limitations.
Trench boxes and shields
A trench box is a protective shield placed in an excavation. Unlike some shoring systems, a shield may not prevent all ground movement; its primary role is to protect workers inside the box if the trench wall fails.
This distinction matters. If nearby structures, roads, or utilities must be protected from movement, a shield alone may not be enough. If the main risk is worker protection inside a utility trench, a correctly selected and placed trench box may be suitable.
Soldier piles and lagging
Soldier piles and lagging use vertical steel piles installed at intervals, with timber, precast concrete, or steel lagging placed between them as excavation proceeds. The piles resist bending; the lagging retains the soil between piles.
This method is common for basement excavations and retaining temporary cuts. It can be combined with internal struts, rakers, or ground anchors where cantilever action alone is not enough.
Sheet piles
Sheet piles are interlocking steel, concrete, vinyl, or timber sections driven or vibrated into the ground to form a continuous retaining wall. They are useful where groundwater control, tight sites, or continuous earth retention are important.
Steel sheet piles are common for deep excavations, cofferdams, waterfront works, and temporary retaining walls. Installation vibration, driving refusal, noise, and effects on adjacent structures must be considered.
Secant pile, contiguous pile and diaphragm walls
These systems are often used for deeper basements and urban excavations. Although they may become part of the permanent works, they also provide temporary support during excavation. They are stiffer than many light shoring systems and can reduce ground movement when designed and built correctly.
They are usually selected where movement control, water control, site boundaries, or depth make simpler systems unsuitable.
Raking shores, flying shores and dead shores
Traditional building shoring terms are still useful:
- Raking shores are inclined supports that brace a wall from the side. They resist lateral movement.
- Flying shores span between two structures to support or brace party walls without bearing on the ground between them.
- Dead shores carry vertical loads, often through needles inserted through or below a wall while work is done beneath.
These are common in alteration, heritage, facade retention, and repair work. For a complementary overview of system types, see shoring in construction types, uses and safety.
How to Select the Right Shoring Method
Selecting shoring starts with the problem, not the product. The right question is: what movement or load must be controlled, for how long, and within what constraints?
Key selection factors include:
- Purpose of support: earth retention, vertical load support, lateral building restraint, formwork support, emergency stabilisation, or a combination.
- Load magnitude: soil pressure, water pressure, building loads, construction live loads, equipment loads, surcharge, wind, vibration, and impact.
- Ground conditions: soil type, strength, groundwater, layering, fill, rock, contamination, and variability across the site.
- Excavation geometry: depth, width, plan shape, working space, proximity to boundaries, and sequence of excavation.
- Movement tolerance: whether small movements are acceptable, or whether adjacent structures and utilities require very tight control.
- Access and buildability: craneage, headroom, plant access, installation from above, traffic constraints, and working around services.
- Duration: hours, days, months, or longer. Durability, corrosion, weather exposure, and inspection frequency change with duration.
- Removal method: whether the system can be removed safely without destabilising the work or damaging the permanent structure.
For excavation shoring, geotechnical information is critical. Poor assumptions about soil and groundwater are a common source of temporary works problems. If the project involves significant excavation, review the ground investigation and testing approach early; see soil testing in a construction project.
Shoring Design Loads and Engineering Considerations
Shoring design is temporary works engineering. Even if the system is temporary, failure can be immediate and severe, so it must be designed with the same discipline as permanent work.
Loads to consider
Common shoring design loads include:
- Dead loads: self-weight of the supported structure, formwork, wet concrete, shoring components, and permanent materials.
- Construction live loads: workers, tools, stored materials, small equipment, concrete placement loads, and temporary access loads.
- Earth pressure: lateral pressure from soil, including effects of soil type, excavation depth, compaction, sloping ground, and wall movement.
- Surcharge loads: loads near an excavation from cranes, trucks, excavators, stockpiles, foundations, roads, and adjacent buildings.
- Water pressure: groundwater, perched water, rainwater, seepage, and hydrostatic pressure where drainage is not relieved.
- Lateral loads: wind, impact, vibration, out-of-plumb effects, and horizontal forces from concrete placement or demolition operations.
- Dynamic and accidental loads: plant impact, dropped materials, vibration from piling or traffic, and emergency conditions where relevant.
Load path and stability
The designer must define a complete load path from the supported element into the ground or another stable structure. A prop under a beam is only useful if the prop has adequate capacity, the head connection distributes load, the base does not punch or settle, and the floor or soil below can carry the reaction.
For excavations, stability checks may include wall bending, strut compression, anchor capacity, basal heave, sliding, overturning, bearing failure, hydraulic uplift, piping, and global slope stability. The exact checks depend on the system and ground conditions.
Deflection and movement control
Capacity is not the only design issue. A shoring system can be strong enough not to fail, but flexible enough to allow damaging movement. This matters near existing buildings, buried utilities, pavements, rail lines, brittle finishes, and heritage structures.
Stiffer systems, preloaded struts, closer prop spacing, better groundwater control, and staged excavation may be needed where movement limits are tight.
Connections, eccentricity and bracing
Temporary works often fail at details: a prop not centred under load, a missing brace, an inadequate base plate, a wedge knocked loose, or a connection that was assumed pinned but behaves unpredictably. Design drawings should show member sizes, spacing, bracing, bearing details, connection requirements, installation tolerances, and restrictions on loading.
For proprietary systems, the design must match the manufacturer’s data and limitations. Do not mix components, exceed extension limits, omit bracing, or assume a catalogue capacity applies to a different configuration.
Shoring Installation and Removal Sequence
Shoring is sequence-dependent. A design that is safe in its final temporary configuration can be unsafe if installed in the wrong order or removed too early.
Typical installation steps
- Confirm conditions: check drawings, permits, underground services, adjacent structures, ground conditions, access, and exclusion zones.
- Review the temporary works design: confirm the approved drawings, load limits, sequence, inspection points, and hold points.
- Prepare bearing areas: level and compact ground, install sole plates or grillages, verify slab capacity, and provide drainage where needed.
- Install primary supports: place piles, sheeting, props, towers, frames, needles, or walers as specified.
- Add bracing and connections: install ties, cross-bracing, wedges, pins, bolts, struts, anchors, and locking devices before loading where required.
- Apply preload if specified: jack or tighten struts to the required level when the design calls for it.
- Excavate, demolish, or build in stages: proceed only to the depth or stage allowed by the design before adding the next support level.
- Inspect before loading: verify line, level, plumb, bearing, member condition, connection, bracing, and clearances.
For example, in a strutted excavation, the sequence may require excavation to the first strut level, installation and preloading of struts, then excavation to the next level. Excavating to full depth first and “adding the struts later” can overload the wall and trigger excessive movement or collapse.
Removal and reshoring
Removal is not simply installation in reverse, although it is often planned that way. Before removing shores, the permanent structure must have enough strength and continuity to carry the load. Concrete must have reached the required strength; beams, slabs, walls, anchors, or frames must be connected; backfill may need to be placed and compacted in stages.
In multi-storey concrete work, reshoring may be needed as forms are stripped. The goal is to transfer load gradually and avoid overloading young slabs below. Removal drawings should state the sequence, minimum strength or approval requirements, and any temporary load restrictions after stripping.
Inspection, Monitoring and Safety Requirements
Shoring safety depends on design, installation, use, inspection, and change control. Most failures are not mysterious; they come from missing information, changed site conditions, overloaded systems, poor workmanship, or removal of critical elements.
Inspection checkpoints
Inspections should be performed by competent personnel before use, after changes, after severe weather or vibration events, and at regular intervals during the work. Typical checks include:
- Correct system, member sizes, spacing, orientation, and layout compared with the approved design.
- Sound bearing at bases, sole plates, grillages, footings, slabs, or ground.
- Props plumb and within permitted extension limits.
- Bracing, pins, clips, bolts, wedges, locks, and anchors installed correctly.
- No visible damage, buckling, corrosion, cracked timber, bent members, missing parts, or overloaded components.
- No unapproved excavation, stockpiling, plant loading, water buildup, or vibration near the system.
- Ground movement, cracking, settlement, wall deflection, or distress in adjacent structures.
- Access, egress, edge protection, exclusion zones, lighting, and emergency arrangements in place.
Monitoring
Monitoring is needed when movement could affect safety or property. Depending on the project, this may include survey points, settlement markers, inclinometers, crack gauges, vibration monitoring, groundwater readings, strut load cells, or regular photographic records.
Monitoring only helps if trigger levels and actions are defined in advance. A practical monitoring plan states what is measured, how often, who reviews it, what values are acceptable, and what happens if readings exceed limits.
Change control and site discipline
Temporary works are vulnerable to informal site changes. A crew may move a prop to create access, stockpile material beside an excavation, cut a brace that is “in the way”, or use a shored slab for storage beyond its allowed load. These actions can invalidate the design.
Good control means the site team understands the load limits and no-change zones. Any proposed modification should go back to the temporary works designer or responsible engineer before work proceeds.
Risk planning
Shoring should be included in construction risk planning, not treated as a last-minute site fix. The risk review should cover collapse, excavation failure, service strikes, groundwater, adjacent property damage, worker access, lifting, emergency rescue, and removal sequence. For a structured approach, see risk analysis in construction planning and execution.
For engineers building their site fundamentals, temporary works and construction sequencing are core skills. You can also explore the civil construction engineer bootcamp.
Closing Thoughts
Shoring in construction is temporary, but it is never secondary. The safest projects treat shoring as engineered work: understand what needs support, select a method that suits the ground and structure, design a complete load path, install it in the correct sequence, inspect it continuously, and remove it only when the permanent works can safely take over.